Procurement – FWE Western Energy https://fwe-services.com Thu, 20 Nov 2025 09:18:22 +0000 en-US hourly 1 https://wordpress.org/?v=7.1.3 Engineering, Procurement, Installation and Commissioning for JISIKE Associated Gas Compressor Station https://fwe-services.com/rt-portfolios/engineering-procurement-installation-and-commissioning-for-jisike-associated-gas-compressor-station/ Wed, 19 Nov 2025 09:15:36 +0000 https://fwe-services.com/?post_type=rt-portfolios&p=12093

Engineering, Procurement, Installation and Commissioning for JISIKE Associated Gas Compressor Station

Project Information
Clients:
Seplat Energy PLC
Category:
Procurement, Installation and Commissioning
Complete Date:
2024
Project Location:
Jisike Field
Project Brief

FWE Western Energy is currently engaged in the SEPLAT Jisike EPIC Contract, providing full support through the Engineering, Procurement, Installation, and Commissioning phases of the project. The scope covers the delivery of essential equipment, materials, technical services, and field support required for SEPLAT’s operations within the Jisike field.

As part of this contract, we are responsible for coordinating all procurement activities, managing certified suppliers, overseeing logistics and inspection, and ensuring that all project materials meet SEPLAT’s strict quality and safety standards. Our team also provides installation support, technical documentation, and compliance reporting throughout the execution period.

This project highlights our capability to deliver reliable, high-quality solutions within the Nigerian oil and gas sector. Through strong project management, strict adherence to industry standards, and full alignment with Nigerian Content requirements, we continue to support SEPLAT’s operational goals and contribute to safe, efficient, and sustainable field development.

]]>
Design, Procurement, Installation and Commissioning of a LACT Unit for OML 147 https://fwe-services.com/rt-portfolios/design-procurement-installation-and-commissioning-of-a-lact-unit-for-oml-147/ Sat, 01 Nov 2025 21:42:52 +0000 https://fwe-services.com/?post_type=rt-portfolios&p=11814

Design, Procurement, Installation and Commissioning of a LACT Unit for OML 147 and The Decommissioning of the existing OML 147 LACT Unit at Ogharefe Flow Station

Project Information
Clients:
PAN OCEAN
Category:
Procurement
Complete Date:
2024 - On Going
Project Location:
Ogharefe Flow Station
Project Brief

FWE Western Energy Limited is currently executing the design, procurement, installation, and commissioning of a new Lease Automatic Custody Transfer (LACT) unit for Pan Ocean Oil Corporation’s OML 147 From 2024 – Till Date. The project also included the safe decommissioning and removal of the existing LACT unit at the Ogharefe Flow Station. We covered end-to-end project delivery, including detailed engineering design, equipment sourcing, fabrication, construction, testing, and system commissioning to achieve optimal metering accuracy and reliability. FWE ensured that all activities were carried out in compliance with Pan Ocean’s operational standards, industry best practices, and regulatory safety requirements.

Below are the works done in Pan Ocean

Stringing, Fit-Up and Welding Of 6” Line Pipes from The LACT Unit to The Valve Pit
Stringing, Fit-Up and Welding Of 6” Line Pipes from The LACT Unit to The Valve Pit
Fit-Up and Welding of The Fabricated Piping Spools
Fit-Up and Welding of The Fabricated Piping Spools
Manual Excavation and Probing Of 10” Discharge Lines of The Tanks
Thrust Boring Activities on Road Crossing
]]>
Operation and Maintenance of Jisike Compressor https://fwe-services.com/rt-portfolios/operation-and-maintenance-of-jisike-compressor/ Sat, 01 Nov 2025 21:28:38 +0000 https://fwe-services.com/?post_type=rt-portfolios&p=11795

Operation and Maintenance of Jisike Compressor

Project Information
Clients:
SEPLAT Enegy Plc
Category:
EPIC Engineering, Procurement ,Installation and Commissioning
Complete Date:
2024 - On Going
Project Location:
OML 53
Project Brief

FWE Western Energy Limited was engaged by Seplat Energy Plc to execute Operation and Maintenace of the Jisike Compressor Station in OML 53. The project commenced in 2024 and is currently ongoing.

The scope covers the complete delivery of compressor facilities and auxiliary systems, including detailed design, equipment procurement, installation, commissioning, and performance optimization. FWE’s role ensures seamless integration, optimum performance, and long-term reliability of the compression system. All project activities are being executed in strict compliance with Seplat’s HSE policies and asset integrity standards, emphasizing quality, safety, and operational excellence throughout the project lifecycle.

]]>